Same question, same model, same tools: the two reports
One run per harness, the run closest to its three-run average. Reports are shown as the harnesses wrote them. Scroll each column.
Twenty of the 31 have contracted data-center load large enough to rank. Southern and AEP come out on top. Southern combines 21 GW of contracts that carry minimum bills with a very small remaining equity need. AEP has by far the most contracted load, though its own figure fails the grid-operator check and has to be cut heavily.
Most figures come from each company's Q3-2026 call, deck and 10-Q, retrieved through Samaya's summaries; I did not open the primary documents. Market caps are November 10 closes.
| Group | Why it isn't ranked |
|---|---|
| American Water, Atmos | No data-center load or data-center capex found in their latest calls, decks or 10-Qs. |
| Con Ed, Eversource, Edison International | Data-center load is essentially nil. New York and New England grid forecasts show roughly 0.1–2.6 GW of large load in total. Edison also carries Eaton fire liability. |
| PSEG | No contracted load, only about 11.8 GW of inquiries, which management calls mostly small edge sites. Any upside sits in its unregulated nuclear plants. |
| AES | Agreed to be taken private at $15.00 cash; the stock is at $14.92, so shareholders get no upside. |
| Dominion | 12.2 GW under signed contracts in Virginia, the strongest data-center zone in PJM. But it is being bought by NextEra in an all-stock deal (0.8138 NEE shares per share; Virginia hearings began in November). The stock now trades on NextEra's price. |
| Constellation, Vistra, NRG | Power producers, not regulated utilities, so they're listed separately below. Their deals sell power from existing plants, which raises margins rather than a regulated asset base. None plans to issue equity. |
| Company | Contracted data-center load | Capex plan |
|---|---|---|
| AEP | 84 GW "contracted" through 2031: 46 GW Texas (letters of agreement, not firm contracts), 31 GW PJM, 7 GW SPP. Only about 35 GW is firm take-or-pay. | $100B, 2027–31; rate base growing over 13% a year |
| Southern | 21 GW across 33 projects, all with minimum bills, 31 under construction. Its 10-Q says about 20 GW. | $81B through 2030, could reach about $100B |
| PPL | 11.4 GW under signed contracts in Pennsylvania (wires-only there) | $25B, 2027–30 |
| Sempra / Oncor | Texas: 45 GW submitted, about 24 GW classified as firm "base" load by the grid operator (10 GW already connected). Not signed contracts. | Oncor $47.5B and Sempra about $65B, 2026–30 |
| FirstEnergy | 7.9 GW; first sites come online around 2030 | $36B, 2026–30 |
| Pinnacle West | 5.8 GW committed, including about 1.8 GW for TSMC's chip plant; 4.9 GW not yet served | About $10.4B, 2025–28. TSMC-related capex excluded. |
| CenterPoint | About 10 GW firm and 2 GW still under study, per the Texas grid operator's classification. Not signed contracts. | $38.7B, 2026–30 |
| NiSource | 3.9 GW signed (Amazon, Alphabet, Microsoft). Management also says "about 5 GW"; the two aren't reconciled. | $29B, 2027–31 ($40B through 2033) |
| Alliant | 3.4 GW (QTS, Google, Meta) | $15.9B, 2027–30 |
| Exelon | About 11 GW "high-probability", 45% backed by collateralized agreements. Only about 10% online by 2028. | $41.7B, 2026–29; wires-only |
| Evergy | About 2.6 GW (Google, Meta, Digital Realty) | $22.5B, 2026–30 |
| WEC | About 4.5 GW forecast under its large-customer tariff: Microsoft 3.2 GW, Vantage/Oracle 1.3 GW. Not stated as contracted MW. | $47.5B, 2027–31 |
| Entergy | No total disclosed. I estimate about 7 GW from the Meta, Google, AWS and other contracts. | $55B, 2027–30 |
| Ameren | 2.8 GW (Google and Amazon sites in Missouri) | $38.1B, 2027–31 |
| DTE | 2.4 GW approved by regulators (Oracle 1.4 GW, Google 1.0 GW) | $44.2B, 2027–31 |
| Duke | About 7.8 GW signed, plus 15.4 GW late-stage | $103B, 2026–30 |
| Xcel | About 2 GW (Google, QTS, Fermi) | $70B, 2027–31 |
| CMS | One site over 1 GW, not yet in the capex plan | $24.1B, 2026–30 |
| NextEra | Florida utility: nothing signed (targets 8 GW by 2032). Generation arm: about 1.6 GW (Google at Duane Arnold, Point Beach). | About $94.5B, rest of 2026–30 |
| PG&E | 0.64 GW with construction agreements; 12.9 GW pipeline | Guidance beyond 2027 withdrawn for a strategic review |
The haircut column is the share of claimed load I kept: 1.0 if the claim is consistent with the regional forecast, 0.75 if it is partly consistent or the timing is at risk, and 0.5 if it exceeds what the region's forecast can hold.
| Company | What the regional forecast shows | Haircut |
|---|---|---|
| AEP | Fails. Its 46 GW of Texas agreements compares with 66 GW of firm load classified for all of ERCOT. Its 31 GW in PJM compares with about 34 GW of data-center growth PJM accepted for the whole region by 2030; PJM cut the AEP zone by 3.7 GW for 2031. AEP's own 2030 submission to PJM is 19.6 GW. | 0.5, applied to the 35 GW firm subset |
| Southern | No grid operator in its region. Against the Georgia regulator's plan (about 8.5 GW of growth by 2031; 9.9 GW of new resources certified), Georgia's 13.5 GW runs ahead of the plan. Minimum bills and construction underway support it. | 0.75 |
| PPL | PJM has its zone as the fastest-growing (6.4% a year); its 12.8 GW submission for 2030 lines up. PPL, FirstEnergy and AES Ohio together cut near-term requests by 6.5 GW. | 0.75 |
| FirstEnergy | PJM cut its Ohio zone 8.1% for 2031. Its submissions total about 5 GW by 2029, and its load only starts around 2030. | 0.75 |
| Exelon | PJM added only 3.7 GW for ComEd by 2031, against about 9 GW claimed there. | 0.5 |
| Oncor / CenterPoint | Both claims sit inside ERCOT's firm classification, but the grid operator's audit is due in December 2026. Oncor, CenterPoint and AEP Texas together claim more than the 66 GW of firm load ERCOT has classified across its whole grid. Independent analysts expect only about 33 GW of Texas data centers by 2030. | 0.75 |
| NextEra (Florida) | The Florida regional forecast has about 3 GW of data centers statewide over 10 years, versus FPL's 8 GW goal. I excluded the unsigned 8 GW entirely. | Unsigned load excluded |
| PG&E | California's energy commission forecasts 5.8 GW for the whole state by 2040, against 14.7 GW of requests at PG&E. Only the firm 0.64 GW is used. | 1.0 on the firm figure |
| MISO and SPP utilities (Ameren, WEC, Alliant, NiSource, DTE, CMS, Evergy, Xcel, Entergy) | Consistent. MISO expects about 20 GW of data centers by 2030 and lists Ameren at 2.9 GW, Alliant at 3.4 GW and WEC at 3.9 GW. SPP shows 9.6 GW under signed service agreements region-wide. | 1.0 (Entergy 0.75, since it gives no total) |
| Duke, Pinnacle West | Consistent with their state resource plans. | 1.0 |
The wider evidence points the same way. PJM accepted only about 57% of what utilities submitted for 2030. NERC, Grid Strategies and FERC (June 2026 orders) all flag projects being counted more than once.
This is planned new common and equity-like issuance over each plan period, as a share of today's market cap, per year.
The load score is credible GW per $10B of market cap. It applies the step 2 haircut, then halves the result for wires-only utilities, which earn on transmission spending but don't own the new generation. The composite weights the load rank at 60% and the equity rank at 40%.
| Rank | Company | Credible GW per $10B | Equity % per year | Main risk |
|---|---|---|---|---|
| 1 | AEP | 2.5 | 1.5 | Its own headline load figure fails the regional check |
| 2 | Southern | 1.5 | 0.5 | Rates frozen in Georgia and Alabama through 2029 |
| 3 | NiSource | 1.8 | 2.1 | Gas plant delays; Microsoft contract still needs approval |
| 4 | Pinnacle West | 3.8 | 2.9 | Includes TSMC; rate case pending; plan runs only to 2028 |
| 5 | PPL | 1.6 | 2.8 | Wires-only in Pennsylvania; near-term cuts |
| 6 | FirstEnergy | 1.1 | 1.5 | Load arrives in 2030 or later; mostly wires-only |
| 7 | Sempra | 0.8 | 0.2 | Texas audit; California drag |
| 8 | WEC | 1.2 | 2.7 | Wisconsin regulator cut its allowed return to 9.5% |
| 9 | Alliant | 1.8 | 3.6 | Heaviest dilution among those with solid load |
| 10 | Entergy | 1.0 | 2.4 | No total disclosed; Meta approvals pending |
| 11 | Evergy | 1.3 | 3.2 | Kansas and Missouri regulatory decisions pending |
| 12 | PG&E | 0.2 | 0 | Wildfire risk; strategic review |
| 13 | CenterPoint | 1.4 | 3.7 | Texas audit; highest dilution |
| 14 | Exelon | 0.6 | 1.8 | Slow ramp; wires-only |
| 15 | Duke | 0.8 | 2.5 | Data centers are small relative to its size |
| 16 | Ameren | 0.9 | 3.2 | Construction timing |
| 17 | NextEra | 0.1 | 1.3 | Florida utility has nothing signed yet |
| 18 | DTE | 0.8 | 3.1 | Rate case due February 2027 |
| 19 | Xcel | 0.4 | 3.1 | Most upside not in the plan; negative Moody's outlook |
| 20 | CMS | 0.5 | 3.5 | Site not in the plan; customer unnamed |
Power producers (separate list): 1. Constellation: about 4.6 GW signed with named hyperscalers (Microsoft, Meta, Amazon, Google), plus a 2.7 GW Google load-following deal, and a $5B buyback. 2. Vistra: about 4.4 GW signed (AWS, Meta, Microsoft), with at least $1B a year of buybacks. 3. NRG: nothing signed yet.
The scoring script is at /tmp/cc_work/scripts/rank.py if you want to change the haircuts or the 60/40 weights.
Sources: company Q3-2026 calls, decks and 10-Qs via Samaya. Grid forecasts: PJM 2026 Load Report, PJM Inside Lines, Utility Dive on the PJM forecast, ERCOT preliminary forecast, ERCOT adjustment notice, NERC 2025 LTRA, Grid Strategies LTRA review. Merger: Switchgear Magazine, VPM.
Ranking method: Composite = rank on contracted DC load as a share of the regional grid forecast (D1) + rank on estimated equity need (D2), equal weights. Utilities with disclosed contracted load (17) rank above electric utilities without it (12), with water and gas-only names last. Without that gate, EIX, PCG, PEG and SRE (rank-sum 27.5, zero equity) would rank ahead of DUK, SO and AEP. Equity need uses management's equity plan where disclosed; otherwise
| Utility | Ticker | Grid Operator | Contracted DC Load (GW) | Pipeline DC Load (GW) | 5-yr Capex Plan ($B) | Equity Need ($B) | EPS Growth Guide | Rank | Source Citations |
|---|---|---|---|---|---|---|---|---|---|
| Constellation Energy | CEG | PJM (also ISO-NE, NYISO, ERCOT, MISO) | 8.5 (generator PPAs, mostly existing fleet) | Not disclosed | Not disclosed (2-yr: ~5.7 2026, ~4.7 2027) | 0 (no equity program; $5B buyback) | Base EPS ≥20% CAGR 2026-2029 | 1 | Transcript Q3'26 2; 10-K 3; Inv. pres. 4 |
| NiSource | NI | MISO | 3.9 signed customer requirement (~5 GenCo capacity) | Up to 9 total by 2035 (~4 beyond signed) | 29.0 (2027-2031) | ~2.5 ($0.4-0.6B/yr maintenance) | 10-11% (2027-2033) | 2 | Transcript 5; Inv. pres. 6,7 ; PR 8; Equity 9 |
| Vistra Corp. | VST | ERCOT / PJM | 1.2 (AWS Comanche Peak PPA) | Not disclosed | Not disclosed (~2.75 2026E, ~3.15 2027E) | 0 (VA SD OCF less dividends exceeds capex) | Not given | 3 | 10-Q 10; Transcript 11; Inv. pres. 12; VA SD 13 |
| NRG Energy | NRG | ERCOT / PJM | 0.445 signed | 1.2 (expandable to 2.4; not definitive) | Not disclosed (VA SD ~4.7 FY26-30) | 0 | >14% adj. EPS CAGR through 2030 | 4 | Transcript 14; Inv. pres. 15; 10-Q 16; VA SD 17 |
| FirstEnergy | FE | PJM | 7.9 | 19 (~4 in active negotiation) | 36.0 (2026-2030) | ~2.0 (up to $2B through 2030) | Near top of 6-8% through 2030 | 5 | Transcript 18; Inv. pres. 19,20 ; PR 21; Equity 22 |
| Alliant Energy | LNT | MISO | 3.4 | 2-4 (advanced prospects) | 15.9 (2027-2030, 4-yr) | ~2.7 (2027-2030) | 8%+ 2027-2030 | 6 | 8-K 23; Transcript 24; Inv. pres. 25; 10-Q 26 |
| PPL | PPL | PJM | 11.4 PA ESAs (+2.3 KY reimbursement agreements, not ESAs) | 35.3 PA advanced-stage; 12.8 KY | 25.0 (2027-2030, 4-yr) | ~4.5 ($3B remaining + ~$1.5B forwards) | 7-9% through 2030 | 7 | Transcript 27,28 ; Inv. pres./PR 29; Equity 30 |
| WEC Energy Group | WEC | MISO | 4.5 tariff-backed (Microsoft 3.2 + Oracle 1.3) | No queue figure | 47.5 (2027-2031) | ~5.5 (2026-2030 plan, pre-$47.5B) | 7-9%+ 2027-2031 | 8 | Transcript 31,32 ; Inv. pres. 33; 8-K 34 |
| Evergy | EVRG | SPP | 2.6 (5 ESAs) | Tier 1 2.0-2.5; Tier 2 1.0-2.0; Tier 3 >10 | 21.6 (2026-2030; raised to 22.5) | 3.3 | 6-8%+ through 2030 | 9 | Transcript 35; Inv. pres. 36,37 ; 10-K 38 |
| Ameren | AEE | MISO | 2.8 | 5.6 (1.2 construction agreements + 4.4 completed studies) | 38.1 (2027-2031) | ~5.0 | 8-10% 2027-2031 | 10 | 10-Q 39; Inv. pres. 40; Earnings materials 41,42 |
| Dominion Energy | D | PJM (DOM) | 12.2 (ESA tier) | 42.6 pre-ESA (ELOA 32.8 + CLOA 9.8) | ~65 (2026-2030) | ~6.5 (~10% common equity in mix) | 5-7% through 2030 | 11 | Inv. pres. 43,44,45 ; Transcript 46; VA SD 47 |
| Duke Energy | DUK | Non-RTO (Carolinas); Ohio PJM, Indiana MISO | 7.8 | 15.4 late-stage | 103 (2026-2030) | 10.0 (2027-2030) | 5-7% through 2030 | 12 | Transcript 48,49 ; 10-Q/IR 50; Equity 51 |
| American Electric Power | AEP | PJM / ERCOT / SPP | 84 through 2031 (ERCOT 46, PJM 31, SPP 7) | ~195 interconnection queue | 100.4 (2027-2031) | ~9.7 (ATM 4 + forwards 4.8 + DRIP 0.9) | 9-11% 2027-2031 | 13 | Transcript 1,52 ; Inv. pres. 53; 10-Q 54; Financing 55 |
| Exelon | EXC | PJM | ~2 (TSA-backed; Q2 call cited 4) | ~9 high-probability remaining + ~23 future | Not disclosed 5-yr (41.7, 2026-2029) | 3.4 (through 2029) | Near top of 5-7% 2025-2029 | 14 | Inv. pres. 56,57 ; Transcript 58; 8-K 59 |
| Southern Company | SO | Non-RTO (Southeast) | 21 (33 projects) | >75 prospective + 5 late-stage + 2 finalizing | 81 base (deck shows 85) | ~12.0 (>$10B secured) | 7-8% from 2028 base | 15 | Transcript 60; Inv. pres. 61,62,63 |
| DTE Energy | DTE | MISO | 2.4 (Oracle 1.4 + Google 1.0) | 5-6 | ~44 (2027-2031) | ~5.0 (~$1B/yr) | >9% through 2031 | 16 | Inv. pres. 64,65 ; Earnings materials 66 |
| Xcel Energy | XEL | MISO / SPP; PSCo non-RTO | ~2 | >20 high-probability | 70 (2027-2031) | 8.0 (~40% contracted) | 9%+ avg through 2031 | 17 | Transcript 67; Inv. pres. 68; 10-Q 69,70 |
| Sempra | SRE | ERCOT (Oncor) | Not disclosed | 45 Batch Zero conditional | 64.9 (2026-2030) | 0 | 7-9% | 18 | Inv. pres. 71,72 ; Transcript 73; PR 74 |
| PG&E Corporation | PCG | CAISO | Not disclosed (1.8 planning assumption) | 12.87 | Not disclosed (5-yr plan withdrawn) | 0 (through 2030) | Withdrawn beyond 2027 (2027 +9%) | 19 | Transcript 75; Inv. pres. 76; 10-Q 77 |
| Edison International | EIX | CAISO | Not disclosed | Not disclosed | 38-41 (2026-2030) | 0 | 5-7% through 2030 | 20 | Transcript 78; Inv. pres. 79; 10-Q 80 |
| Public Service Enterprise Group | PEG | PJM (PS) | Not disclosed | Not disclosed | 24-28 (2026-2030) | 0 | 6-8% through 2030 | 21 | Transcript 81; Inv. pres. 82,83 |
| Eversource Energy | ES | ISO-NE | Not disclosed | Not disclosed | 26.5 (2026-2030) | ~0.95 ($0.8-1.1B) | 5-7% through 2030 | 22 | Conference transcript 84; Inv. pres./10-K 85; 8-K 86 |
| Pinnacle West | PNW | Non-RTO (Arizona) | Not disclosed as DC-only (5.8 total committed incl. TSMC 1.88) | ~20 uncommitted queue | Not disclosed (3-yr APS 10.35) | ~1.1 (2026-2028) | 5-7% (2024-2028) | 23 | Transcript 87,88 ; Inv. pres. 89,90 |
| Consolidated Edison | ED | NYISO | Not disclosed | Not disclosed | 38 (2026-2030) | ~2.0 (ATM proxy; 5-yr need not disclosed) | 6-7% (2026-2030) | 24 | Transcript 91; 8-K 92 |
| CMS Energy | CMS | MISO | Not disclosed as GW (one large DC agreement signed) | ~9 | 24 (2026-2030) | ~3.75 | 6-8% (toward high end) | 25 | Transcript 93,94 ; Inv. pres. 95,96 |
| CenterPoint Energy | CNP | ERCOT | Not disclosed | ~14 Batch Zero eligible | 38.7 (2026-2030) | ~4.0 (through 2030) | 7-9% (mid-to-high end) | 26 | Transcript 97,98 ; 10-Q 99; Inv. pres. 100 |
| Entergy | ETR | MISO | Not disclosed as GW | 7-12 hyperscale (probability-weighted) + 3-5 industrial | 55 (2027-2030, 4-yr) | 5.2 (2027-2030) | >8% through 2030 | 27 | Transcript 101,102 ; Inv. pres. 103; 10-Q 104 |
| NextEra Energy | NEE | Non-RTO (FRCC) | Not disclosed as DC load | >20 large-load opportunity set | 72 (2026-2030) | ~7.2 (company: $12-17B through 2032) | 8%+ through 2032 | 28 | Transcript 105,106 ; Inv. pres. 107,108 ; VA SD 17 |
| The AES Corporation | AES | PJM (Ohio) / MISO (Indiana) | Not disclosed (Monrovia ESA, no MW) | Not disclosed | Not disclosed (growth capex 20-22, 2025-2027) | Not disclosed (take-private pending) | 7-9% through 2027 | 29 | 10-Q 109; Inv. pres. 110; PR 111; Proxy 112 |
| American Water Works | AWK | N/A (water) | Not disclosed (no DC exposure) | Not disclosed | 20+ (2026-2030) | 2.5 | 7-9% | 30 | Transcript/PR 113,114 ; Financing plan 115 |
| Atmos Energy | ATO | N/A (gas-only) | Not disclosed (no DC exposure) | Not disclosed | ~29 (FY2027-2031) | ~8.7 (formula) | 6-8% through FY2031 | 31 | Transcript 116; Inv. pres. 117,118 ; VA SD 119 |
Plan windows differ: LNT, ETR, PPL (2027-2030) and EXC (2026-2029) are four-year plans; AEE, AEP, DTE, NI, WEC, XEL and ATO run 2027-2031; others with plans run 2026-2030. CEG, NRG, PCG, PNW, AES and VST have no five-year capex plan. Visible Alpha SD data was not usable for DTE or PPL, so their equity figures rest on company plans.
| Ticker | Region / benchmark | Contracted GW | Share of benchmark | Materiality |
|---|---|---|---|---|
| AEP | PJM + ERCOT + SPP | 84 | Dominant | |
| DUK | Carolinas Resource Plan 2026-2030 increment ( | 7.8 | Exceeds benchmark | |
| SO | Georgia Power 2025 IRP (+9.7 GW by 2034) | 21 | Exceeds benchmark | |
| WEC | MISO 2030 DC peak (20.5 GW) | 4.5 | Meaningful | |
| NI | MISO | 3.9 | Meaningful | |
| D | PJM 10-yr increase (65.7 GW) | 12.2 | Meaningful | |
| PPL | PJM | 11.4 | Meaningful | |
| LNT | MISO | 3.4 | Meaningful | |
| AEE | MISO | 2.8 | Meaningful | |
| CEG | PJM | 8.5 | Meaningful (mostly existing fleet) | |
| FE | PJM | 7.9 | Meaningful | |
| DTE | MISO | 2.4 | Meaningful | |
| XEL | MISO | 2 | Moderate | |
| EVRG | SPP large-load requests (~30 GW) | 2.6 | Moderate | |
| EXC | PJM | ~2 | Immaterial | |
| VST | ERCOT Batch Zero base load (66.4 GW) | 1.2 | Immaterial | |
| NRG | ERCOT | 0.445 | Immaterial |
CMS, CNP, ED, EIX, ETR, ES, NEE, PCG, PEG, SRE, AES and PNW do not disclose contracted DC GW, so their share is not disclosed; AWK and ATO have no DC exposure.
| Ticker | Equity ($B) | Capex ($B) | Equity / capex | Subsector |
|---|---|---|---|---|
| ATO | 8.7 | 29 | Gas LDC (formula-based) | |
| PPL | 4.5 | 25 | Electric and gas | |
| LNT | 2.7 | 15.9 | Electric and gas | |
| WEC | 5.5 | 33.3 (prior plan ex-ATC) | Electric and gas | |
| CMS | 3.75 | 24 | Electric and gas | |
| EVRG | 3.3 | 21.6 | Electric | |
| SO | 12 | 81 | Electric and gas | |
| AEE | 5.0 | 38.1 | Electric and gas | |
| AWK | 2.5 | 20 | Water | |
| XEL | 8 | 70 | Electric and gas | |
| DTE | 5 | 44 | Electric and gas | |
| CNP | 4 | 38.7 | Electric and gas | |
| D | 6.5 | 65 | Electric and gas | |
| NEE | 7.2 | 72 | Electric | |
| DUK | 10 | 103 | Electric and gas | |
| AEP | 9.7 | 100.4 | Electric | |
| ETR | 5.2 | 55 | Electric | |
| NI | 2.5 | 29 | Electric and gas | |
| EXC | 3.4 | 41.7 | Electric T&D | |
| FE | 2 | 36 | Electric T&D | |
| ED | 2 | 38 | Electric and gas (ATM proxy) | |
| ES | 0.95 | 26.5 | Electric, gas and water | |
| EIX, PEG, SRE, PCG | 0 | See master table | 0% | No new common equity |
| Subsector | Names | Aggregate plan capex ($B) | Weighted equity / capex |
|---|---|---|---|
| Electric | AEP, EIX, ETR, EVRG, EXC, FE, NEE | ||
| Multi-utility (electric and gas) | LNT, AEE, CMS, CNP, ED, DTE, D, DUK, ES, NI, PPL, PEG, SRE, SO, WEC, XEL |
Subsector grouping follows each company's business mix (electric-only vs. electric and gas); PCG and PNW are excluded for lack of a five-year plan, and plan windows differ. Multi-utilities fund a slightly larger share of capex with equity, driven by SO, DUK and XEL; T&D-heavy electric names (FE, EXC) carry the lowest intensity. IPPs (CEG, VST, NRG) fund growth from free cash flow and need no equity.
| Rank | Ticker | Contracted ÷ pipeline (GW) | Ratio |
|---|---|---|---|
| 1 | LNT | 3.4 ÷ 3 (midpoint of 2-4) | |
| 2 | NI | 3.9 ÷ 4 | |
| 3 | DUK | 7.8 ÷ 15.4 | |
| 4 | AEE | 2.8 ÷ 5.6 | |
| 5 | DTE | 2.4 ÷ 5.5 (midpoint of 5-6) | |
| 6 | AEP | 84 ÷ 195 | |
| 7 | FE | 7.9 ÷ 19 | |
| 8 | NRG | 0.445 ÷ 1.2 | |
| 9 | PPL | 11.4 ÷ 35.3 | |
| 10 | D | 12.2 ÷ 42.6 | |
| 11 | SO | 21 ÷ 82 | |
| 12 | EVRG | 2.6 ÷ 13.75 | |
| 13 | XEL | 2 ÷ 20 | |
| 14 | EXC | 2 ÷ 32 |
The ratio cannot be computed for CEG, VST, WEC and names without a contracted or pipeline figure. Contract discipline is explicit at the leaders: Alliant aims "not to present the biggest number" (Transcript) 160; Duke is "not counting anything until it hits the ESA level" 161; FirstEnergy puts no uncontracted demand in plan 162; Ameren includes only ESA-backed sales 163.
| Region | Source | Projection used |
|---|---|---|
| PJM | 2026 Long-Term Load Forecast Report | +65.7 GW summer peak over 10 years to 222,106 MW (2036) 120; data centers 61.1 GW of the increase 121 |
| MISO | 2026 LTLF (Apr 2026 update) | DC peak 1.2 GW (2026) to 20.5 GW (2030) 127; 63% load growth 2026-2046 164 |
| ERCOT | Batch Zero classifications (Sep 3, 2026); preliminary 2026-2032 LTLF; Senate briefing | 66.4 GW base load, 127.9 GW studied 132; LTLF "not a prediction" 133; ~474 GW queue 131 |
| SPP | 2026 ITP scoping; HILL requests | ~30 GW large-load requests 165; 27 HILL requests, 11,163 MW 166 |
| CAISO / CEC | CEC data-center forecast (Jan 2026); 2025-2026 Transmission Plan | 1.8 GW DC growth by 2030 135,167 |
| NYISO | 2026 Gold Book; Power Trends; large-load queue | 13 GW large-load queue by 2030 136,168,169 |
| ISO-NE | 2026 CELT | Large loads add 110-130 MW of peak 137,170 |
| Carolinas (non-RTO) | Duke 2025 Carolinas Resource Plan | DEC 18,633 to 20,998 MW; DEP 12,739 to 13,950 MW (2026-2030) 171 |
| Southeast (non-RTO) | Georgia Power 2025 IRP; NERC 2025 LTRA | +9.7 GW summer peak by 2034 172; SERC-Southeast +4,468 MW 2027-2029 173 |
| Florida (FRCC) | FRCC 2026 Ten-Year Site Plan overview | +9,457 MW firm peak 2026-2035 130 |
| Arizona (APS) | APS load forecast presentation | Peak 8.7 GW (2025) to 12.0 GW (2035); 19 GW uncommitted queue 174 |
| National | NERC aggregate | 224 GW 10-year summer growth 175; an EIA regional load forecast is not available here |